Reinforcement work is schedule-critical
Steel fixing sits directly on the critical path: the pour cannot happen until the reinforcement is fixed and inspected, and a pour that slips usually drags the following floor with it. That is why reinforcement requirements are better raised against the pour programme than against a monthly average headcount.