Before the scope is even final
The outage dates matter more than a finished scope. Dates let availability be checked for the trades a shutdown depends on while the work list is still being written; the scope can be refined afterwards.
- ☐ Send the outage window (start and end dates) as soon as it is known — before the full scope is set, if necessary
- ☐ Estimate the trades most likely to be needed: welders, scaffolders, pipe fitters, riggers, mechanical fitters
- ☐ Flag any welding grade, material or certification requirement you already know about